RSOI Shower/Latrine SOW

26 MAR 05

 

 



STATEMENT OF WORK AND TECHNICAL SPECIFICATIONS FOR SHOWER / LATRINE UNITS

 

PROJECT SUMMARY:  The Contractor shall provide all labor, materials, tools, equipment, and supervision and all other items as necessary to complete the work as described in the Scope of Work (SOW), Section 2, below. The contractor shall perform to the standards in the contract. The Contractor shall conduct all work in a professional manner, in accordance with U.S. traditionally recognized construction practices.

 

SECTION 1: GENERAL REQUIREMENTS

 

1.1 EQUIPMENT: The contractor shall supply all tools and equipment to complete all project requirements. All equipment shall be new and in operable condition. Contractor will provide all fuel, oil, spare parts, tools and mechanics to repair and maintain equipment for 1 year from start of service date. Any broken or damaged equipment will be fixed or replaced with in 24 hours of reported time.

 



Download 264.42 Kb.

Share with your friends:
  1   2   3   4   5   6   7   8   9   ...   24




The database is protected by copyright ©essaydocs.org 2023
send message

    Main page