3.3 Change Control Board Unit Tasks


Change Control Board Administrator:

  1. Upon receipt of a Design Change Request, set up a CCB meeting within 7-10 days, attend the meeting, record the Board’s decision. Upon completion, forward the request with the reason for the recommended approval to the Assistant Commissioner of Capital Program Management for concurrence.

Notify the Project Manager of the decision by forwarding a copy of the signed decision. Also forward a copy to any parties who have additional responsibilities as a result of the Board’s decision.

  1. If the request was recommended for approval without a meeting, the request must be sent to the other members of the CCB, as well as the Capital Program Coordination Unit and the Federal Highway Administration as appropriate, for their comment prior to being forwarded to the Assistant Commissioner of Capital Program Management for concurrence. Any comments received must be resolved and documented prior to requesting concurrence from the Assistant Commissioner. If they cannot be resolved individually, then a CCB meeting should be scheduled to present the request to the full CCB.

Once approved or rejected by the Assistant Commissioner of Capital Program Management, the CCB decision should be sent to Project Manager, all members of the CCB, the Capital Program Coordination Unit, the Project Management Office, and the Federal Highway Administration.

The original request and signed decision are retained in the CCB files housed in the Project Management Office.



Change Control Board Members: Review the Design Change Request and dispose of it by approving it in whole or in part, with or without additional instructions or conditions, or rejecting it. If the request was recommended for approval without a meeting, forward any comments to the CCB Administrator within the requested timeframe.

Directory: transportation -> eng
eng -> Notice of requirement for affirmative action to ensure equal opportunity
eng -> State of new jersey equal employment opportunity for contracts funded by wholly state funds
transportation -> Caddo Kiowa Technology Center Program of Study for Transportation, Distribution & Logistics
transportation -> Network Connection setup for kytc samsung slm cell phones and the tsc2 controller
transportation -> Statement of Qualification for Transit Village Designation Revised November 2012 Introduction
transportation -> Chapter 10. Recommendations Table of Contents
transportation -> U. S. Department of Transportation (dot) ada regulations
eng -> Equal Employment Opportunity Special Provisions Construction Contracts Funded By Wholly State Funds
eng -> New jersey department of transportation step IV non-binding mediation agreement this agreement
eng -> Standard Federal Equal Employment Opportunity Construction Contract Specifications


Share with your friends:
1   2   3   4   5   6   7   8   9   10   11




The database is protected by copyright ©essaydocs.org 2020
send message

    Main page