3.1 Design Unit Tasks


Notify the Project Manager of potential change.

3.2 Project Management Unit Tasks


Project Manager: When a design change in a project appears to be necessary or desirable, complete the Design Change Request form attaching any supporting material and submit it to the Program Manager for review and concurrence. As part of the gathering of supporting information, gain the review and/or approval of the FHWA Area Engineer if Full Oversight. Also, review the scoping history with Project Planning and Development (if previously involved).

Present the issue to the CCB at the scheduled CCB meeting.

If approved, process the changes to the appropriate contract, cost and schedule documents. If rejected, notify the designer.

Program Manager: Review the request for validity, completeness and accuracy. Obtain concurrence from the Director of Project Management and forward the request to the CCB Administrator.

Director: Review and dispose of the request in one of the following ways.

Reject: If not in favor of the proposed change, reject it and return it to the Program Manager.

Concur: Indicate concurrence on the request form and return to the Program Manager for submission to the CCB Administrator to set up a meeting.

Approve: Recommend for approval without a meeting of the CCB. Note the reason for, and any conditions of, approval on the decision page of the Change Request form and forward to the CCB Administrator.


Directory: transportation -> eng
eng -> Notice of requirement for affirmative action to ensure equal opportunity
eng -> State of new jersey equal employment opportunity for contracts funded by wholly state funds
transportation -> Caddo Kiowa Technology Center Program of Study for Transportation, Distribution & Logistics
transportation -> Network Connection setup for kytc samsung slm cell phones and the tsc2 controller
transportation -> Statement of Qualification for Transit Village Designation Revised November 2012 Introduction
transportation -> Chapter 10. Recommendations Table of Contents
transportation -> U. S. Department of Transportation (dot) ada regulations
eng -> Equal Employment Opportunity Special Provisions Construction Contracts Funded By Wholly State Funds
eng -> New jersey department of transportation step IV non-binding mediation agreement this agreement
eng -> Standard Federal Equal Employment Opportunity Construction Contract Specifications


Share with your friends:
1   2   3   4   5   6   7   8   9   10   11




The database is protected by copyright ©essaydocs.org 2020
send message

    Main page