Allowable Costs – State Public Assistance Agency Costs

State public assistance agency costs are (1) defined as all costs allocated or incurred by the State agency except expenditures for financial assistance, medical vendor payments, and payments for services and goods provided directly to program recipients (e.g., day care services); and (2) normally charged to Federal awards by implementing the public assistance cost allocation plan (CAP). The public assistance CAP provides a narrative description of the procedures that are used in identifying, measuring and allocating all costs (direct and indirect) to each of the programs administered or supervised by State public assistance agencies.

Attachment D of A-87 states that since the federally financed programs administered by State public assistance agencies are funded predominantly by HHS, HHS is responsible for the requirements for the development, documentation, submission, negotiation and approval of public assistance CAPs. These requirements are published in Subpart E of 45 CFR part 95.

Major Federal programs typically administered by State public assistance agencies include: Temporary Assistance for Needy Families (CFDA 93.558), Medicaid (CFDA 93.778), Supplemental Nutrition Assistance Program (CFDA 10.561), Child Support Enforcement (CFDA 93.563), Foster Care (CFDA 93.658), Adoption Assistance (CFDA 93.659), and Social Services Block Grant (CFDA 93.667).



1. Compliance Requirements – State Public Assistance Agency Costs

a. Basic GuidelinesRefer to the previous section, “Allowable Costs – State/Local-Wide Central Service Costs, 1.a, Compliance Requirements-Basic Guidelines,” for the guidelines affecting the allowability of costs (direct and indirect) under Federal awards.

b. Selected Items of Cost – Refer to the previous section, “Allowable Costs – State/Local-Wide Central Service Costs 1.b, Compliance Requirements-Selected Items of Cost,” for the principles to establish allowability or unallowability of certain items of cost. These principles apply whether a cost is treated as direct or indirect.

c. Submission Requirements

Unlike most State/local-wide central service CAPs and ICRPs, an annual submission of the public assistance CAP is not required. Once a public assistance CAP is approved, State public assistance agencies are required to promptly submit amendments to the plan if any of the following events occur (45 CFR section 95.509):

(1) The procedures shown in the existing cost allocation plan become outdated because of organizational changes, changes to the Federal law or regulations, or significant changes in the program levels, affecting the validity of the approved cost allocation procedures.

(2) A material defect is discovered in the cost allocation plan.

(3) The State plan for public assistance programs is amended so as to affect the allocation of costs.

(4) Other changes occur which make the allocation basis or procedures in the approved cost allocation plan invalid.

The amendments must be submitted to HHS for review and approval.

d. Documentation Requirements – A State must claim Federal financial participation for costs associated with a program only in accordance with its approved cost allocation plan. The public assistance CAP requirements are contained in 45 CFR section 95.507.

e. Implementation of Approved Public Assistance CAPs – 1Since public assistance CAPs are of a narrative nature, the Federal Government needs assurance that the cost allocation plan has been implemented as approved. This is accomplished by funding agencies’ reviews, single audits, or audits conducted by the cognizant audit agency (A-87, Attachment D, paragraph E.1).



2. Audit Objectives – State Public Assistance Agency Costs

a. Obtain an understanding of internal control over the compliance requirements for State public assistance agency costs, assess risk, and test internal control as required by OMB Circular A-133 §___.500(c).

b. Determine whether the governmental unit complied with the provisions of A-87 as follows:

(1) Direct charges to Federal awards were for allowable costs.

(2) Charges to cost pools allocated to Federal awards through the public assistance CAP were for allowable costs.

(3) The approved public assistance CAP correctly describes the actual procedures used to identify, measure, and allocate costs to each of the programs operated by the State public assistance agency. However, the actual procedures or methods of allocating costs must be in accordance with the applicable cost principles, and produce an equitable and consistent distribution of costs.

(4) Charges to Federal awards are in accordance with the approved public assistance CAP. This does not apply if the auditor first determines that the approved CAP is not in compliance with the applicable cost principles and/or produces an inequitable distribution of costs.

(5) The employee time reporting systems are implemented and operated in accordance with the methodologies described in the approved public assistance CAP.



3. Suggested Internal Control Audit Procedures – State Public Assistance Agency Costs

Refer to the previous section, “Allowable Costs – State/Local-Wide Central Service Costs” items 3.a through 3.c, for suggested internal control audit procedures.



4. Suggested Compliance Audit Procedures – State Public Assistance Agency Costs

a. Consider the results of the testing of internal control in assessing the risk of noncompliance. Use this as the basis for determining the nature, timing, and extent (e.g., number of transactions to be selected) of substantive tests of compliance.

b. Since a significant amount of the costs in the public assistance CAP are allocated based on employee time reporting systems (e.g., effort certification, personnel activity report and/or random moment sampling), it is suggested that the auditor consider the risk when designing the nature, timing, and extent of compliance testing.

c. General Audit Procedures – The following procedures apply to direct charges to Federal awards as well as charges to cost pools that are allocated wholly or partially to Federal awards.

(1) Test a sample of transactions for conformance with:

(a) The criteria contained in the “Basic Guidelines” section of A-87, Attachment A, paragraph C.

(b) The principles to establish allowability or unallowability of certain items of cost (A-87, Attachment B).

(2) If the auditor identifies unallowable costs, the auditor should be aware that directly associated costs might have been charged. Directly associated costs are costs incurred solely as a result of incurring another cost, and would have not been incurred if the other cost had not been incurred. When an unallowable cost is incurred, directly associated costs are also unallowable. For example, occupancy costs related to unallowable general costs of government are also unallowable.

d. Special Audit Procedures for Public Assistance CAPs

(1) Verify that the State public assistance agency is complying with the submission requirements, i.e., an amendment is promptly submitted when any of the events identified in 45 CFR section 95.509 occur.

(2) Verify that public assistance CAP includes the required documentation in accordance with 45 CFR section 95.507.

(3) Testing of the Public Assistance CAP – Test the methods of allocating the costs to ascertain if they are in accordance with the applicable provisions of the cost principles and produce an equitable distribution of costs. Appropriate detailed tests may include:

(a) Examine the results of the employee time reporting systems to ascertain if they are accurate, and are based on the actual effort devoted to the various functional and programmatic activities to which the salary and wage costs are charged.

(b) Since the most significant cost pools in terms of dollars are usually allocated based upon the distribution of income maintenance and social services workers efforts identified through random moment time studies, determine whether the time studies are implemented and operated in accordance with the methodologies described in the approved public assistance CAP. For example, verify the adequacy of the controls governing the conduct and evaluation of the study, determine that the sampled observations were properly selected and performed, the documentation of the observations was properly completed, and that the results of the study were correctly accumulated and applied. Testing may include observing or interviewing staff who participate in the time studies to determine if they are correctly recording their activities.

(c) Test statistical data (e.g., square footage, case counts, salaries and wages) to ascertain if the proposed allocation bases are reasonable, updated as necessary, and do not contain any material omissions.

(4) Testing of Charges Based Upon the Public Assistance CAP – If the approved public assistance CAP is determined to be in compliance with the applicable cost principles and produces an equitable distribution of costs, verify that the methods of charging costs to Federal awards are in accordance with the approved CAP and the provisions of the approval documents issued by HHS. Detailed compliance tests may include:

(a) Verify that the cost allocation schedules, supporting documentation and allocation data are accurate and that the costs are allocated in compliance with the approved CAP.

(b) Reconcile the allocation statistics of labor costs to completed employee time reporting documents (e.g., personnel activity reports or random moment sampling observation forms).

(c) Reconcile the allocation statistics of non-labor costs to allocation data, (e.g., square footage or case counts).

(d) Verify direct charges to supporting documents (e.g., purchase orders).

(e) Reconcile the costs to the Federal claims.

Note: The suggested audit procedures above for internal control and compliance testing may be accomplished using dual-purpose testing.



OMB CIRCULAR A-21
COST PRINCIPLES FOR EDUCATIONAL INSTITUTIONS


Introduction

OMB Circular A-21 (A-21) establishes principles for determining the costs applicable to research and development, training, and other sponsored work performed by educational institutions under grants, contracts, and other agreements with the Federal Government. These agreements are referred to as sponsored agreements. These principles shall be used in determining the allowable direct and indirect costs under those agreements. At educational institutions, indirect costs are accounted for through Facilities & Administrative (F&A) Cost Proposals. F&A costs, for the purpose of A-21, mean costs that are incurred for common or joint objectives and, therefore, cannot be identified readily and specifically with a particular sponsored project, an instructional activity, or any other institutional activity. F&A costs are synonymous with “indirect” costs, as previously used in A-21 and as currently used in Appendices A and B of A-21. As described in A-21, section F.1, the F&A cost categories include: building and equipment depreciation or use allowance; operation and maintenance expenses; interest expenses; general administrative expenses; departmental administration expenses; sponsored project administration expenses; library expenses; and student administration expenses. F&A costs will be referred to as “indirect costs” in this section.



Cognizant Agency

A-21, section G.11.a, defines “cognizant agency” as the Federal agency responsible for negotiating and approving F&A rates for an educational institution on behalf of all Federal agencies. References to “cognizant agency” in this section should not be confused with the cognizant Federal agency for audit responsibilities, which is defined in OMB Circular A-133, Subpart D., §___.400(a). Section G.11 of A-21 assigns cost negotiation cognizance to the Department of Health and Human Services and the Department of Defense, Office of Naval Research.



Availability of Other Information

University Long-Form F&A Cost Proposals

Additional information on indirect cost rates is found in the HHS publication: Best Practices Manual for Reviewing College and University Long-Form Facilities & Administrative Cost Rate Proposals, which is available on the Internet at http://rates.psc.gov/fms/dca/C&U%20Review%20Manual.pdf



Allowable Costs – General Criteria

1. Basic Considerations to Determine Costs

In addition to the general criteria applicable to both direct and indirect costs, the basic guidelines affecting the allowability of costs (direct and indirect) are identified in section C. of A-21. To be allowable under Federal awards, costs must meet the following general criteria:

a. Be reasonable and necessary for the performance and administration of Federal awards (A-21, section C.3).

b. Conform with the allocability provisions of A-21 (A-21, section C.4) or Cost Accounting Standards (CAS) Board for educational institutions, as applicable (see 48 CFR part 9905). See “Allowable Costs - Special Requirements - Cost Accounting Standards and Disclosure Statements” in this section for additional guidance on CAS.)

c. Be given consistent accounting treatment within and between accounting periods. Consistency in accounting requires that costs incurred for the same purpose, in like circumstances, be treated as either direct costs only or indirect costs only with respect to final cost objectives (A-21, sections C.10 and C.11).

d. Conform with the allowability of costs provisions of A-21, or limitations in the program agreement, program regulations, or program statute. When the maximum amount of allowable cost under a limitation is less than the total amount determined in accordance with A-21, the amount not recoverable under a sponsored agreement may not be charged to other sponsored agreements (A-21, section C.7).

e. Be net of all applicable credits, e.g., volume or cash discounts, insurance recoveries, refunds, rebates, trade-ins, adjustments for checks not cashed, and scrap sales (A-21, section C.5).

f. Be supported by appropriate documentation, such as approved purchase orders, receiving reports, vendor invoices, canceled checks, and time and attendance records, and correctly charged as to account, amount, and period. Documentation requirements for salaries and wages, and time and effort distribution are described in A-21. Documentation may be in an electronic form (A-21, section C.4).

g. Be applied uniformly to Federal and non-Federal activities.

h. With respect to fringe benefit allocations, charges, or rates, such allocations, charges, or rates are to be based on the benefits received by different classes of employees within the educational institution.



2. Selected Items of Cost

Section J. of Circular A-21 includes general provisions for selected items of costs. For a listing of these costs, see Exhibit 1 of this part of the Supplement. These principles apply irrespective of whether a particular item of cost is properly treated as a direct cost or an indirect cost. Failure to mention a particular item of cost is not intended to imply that it is either allowable or unallowable; rather, determination as to allowability in each case should be based on the treatment provided for similar or related items of cost.



Allowable Costs – Direct Costs

1. Compliance Requirements – Direct Costs

    1. Direct costs are those costs that can be identified specifically with a particular sponsored project, instructional activity, or any other institutional activity, or that can be directly assigned to such activities relatively easily with a high degree of accuracy. Identification with the sponsored work rather than the nature of the goods and services involved is the determining factor in distinguishing direct from indirect costs of a sponsored agreement.

    2. Costs incurred for the same purpose in like circumstances must be treated consistently. Where an educational institution treats a particular type of cost as a direct cost of sponsored agreements, all costs incurred for the same purpose in like circumstances shall be treated as a direct costs of all activities of the institution.

2. Audit Objectives – Direct Costs

  1. Obtain an understanding of internal control, assess risk, and test internal control as required by OMB Circular A-133 §___.500(c).

b. Determine whether the educational institution complied with the provisions of
A-21 and CAS as follows:

(1) Direct charges to Federal awards were for allowable costs.

(2) Cost accounting practice disclosures, described in the Disclosure Statement (DS-2), including amendments, represented actual practice consistently applied. This objective only applies to non-Federal entities that are required to submit the DS-2.

(3) Costs are not included as both a direct billing and as a component of indirect costs, e.g., excluded from cost pools, if charged directly to Federal awards.



3. Suggested Internal Control Audit Procedures – Direct Costs

a. Using the guidance provided in Part 6 – Internal Control, perform procedures to obtain an understanding of internal control sufficient to plan the audit to support a low assessed level of control risk for the program.

b. Plan the testing of internal control to support a low assessed level of control risk for allowable costs/cost principles and perform the testing of internal control as planned. If internal control over some or all of the compliance requirements is likely to be ineffective, see the alternative procedures in §___.500(c)(3) of OMB Circular A-133, including assessing the control risk at the maximum and considering whether additional compliance tests and reporting are required because of ineffective internal control.

c. Consider the results of the testing of internal control in assessing the risk of noncompliance. Use this as the basis for determining the nature, timing, and extent (e.g., number of transactions to be selected) of substantive tests of compliance.



4. Suggested Compliance Audit Procedures – Direct Costs

Test a sample of transactions for conformance with the following criteria contained in A-21 and CAS, as applicable:

a. If the auditor identifies unallowable direct costs, the auditor should be aware that “directly associated costs” might have been charged. Directly associated costs are costs incurred solely as a result of incurring another cost, and would not have been incurred if the other cost had not been incurred. For example, fringe benefits are “directly associated” with payroll costs. When an unallowable cost is incurred, directly associated costs are also unallowable.

b. Costs were approved by the Federal-awarding agency, if required (see Exhibit 1 in this part of the Supplement for selected items of cost that require agency approval when charged to an award as direct costs).

c. Costs were not included as a cost or used to meet cost-sharing requirements of other federally supported activities of the current or a prior period.

d. Costs represent charges for actual costs, not budgeted or projected amounts.

e. Costs were estimated, accumulated, and reported consistently (A-21, section C.10).

f. Costs incurred for the same purpose, in like circumstances, are either direct costs only or indirect costs only with respect to final cost objectives (A-21, section C.11).

g. Costs charged directly to institutional activities (i.e. research and development, instruction, other institutional activities) are accounted for consistent with their disclosed practices, as described in their DS-2, if applicable (A-21, section C.14).

h. Departmental costs charged direct to institutional activities (i.e. research and development, instruction, other institutional activities) are consistently charged directly, in like circumstances and are in accordance with the provisions of A-21 and CAS. Salaries of administrative and clerical staff should normally be treated as indirect. Direct charging of these costs may be appropriate where a major project or activity explicitly budgets for the administrative or clerical services and the individuals involved can be specifically identified with the project or activity. “Major project” is defined as a project that requires an extensive amount of administrative or clerical support, which is significantly greater than the routine level of such services provided by academic departments. Examples are found in A-21, Exhibit C.

i. Costs for general-purpose equipment charged direct to institution activities (i.e., research and development, instruction, other institutional activities) are consistently charged as direct, were approved by the awarding agency, and are in accordance with the provisions of A-21 and CAS.

j. Salaries and wages charged to Federal awards are allowable to the extent that total compensation to the individual employee conforms to established policies of the institution, are consistently applied, and provided that the charges for work performed directly on sponsored awards have been determined in accordance with and supported by the provisions of A-21, section J.10 as follows:

(1) Distribution of salaries and wages is based on payrolls documented in accordance with the generally accepted practices of the institution.

(2) Apportionment of employees’ salaries and wages which are chargeable to more than one sponsored agreement or other cost objective is accomplished by methods which--

(a) Comply with A-21, sections A.2 and C,

(b) Produce an equitable distribution of charges for employees’ activities, and

(c) Distinguish the employees’ direct activities from their indirect activities.

(3) The payroll distribution is based on an after-the-fact confirmation or determination that costs distributed represent actual costs. Confirmation should be by a responsible person with suitable means of verification that the work was performed. Confirmation by the employee is not required if other responsible persons make appropriate confirmations.



Allowable Costs – Indirect Costs

1. Compliance Requirements – Indirect Costs

a. In order to recover indirect costs, educational institutions must prepare indirect cost rate proposals (ICRPs) in accordance with the guidelines provided in A-21. Educational institutions must submit ICRPs to the cognizant agency for approval (A-21, section G.11).

b. ICRPs prepared by educational institutions are based on the most current financial data supported by the educational institution’s accounting system and audited financial statements. These ICRPs can be used to establish either predetermined rates, fixed rates with carry-forward provisions, or provisional rates (A-21, sections G.4, G.5, and G.6). The ICRP to be used to establish indirect cost rates must be certified by the educational institution in accordance with
A-21, section K.2.

c. Indirect costs are those costs that are incurred for common or joint objectives and, therefore, cannot be identified readily and specifically with a particular sponsored project, an instructional activity, or any other institutional activity.

d. As described in A-21, section F.1, the indirect cost categories include: building and equipment depreciation or use allowance; operation and maintenance expenses; interest expenses; general administrative expenses; departmental administration expenses; sponsored project administration expense; library expenses; and student administration expenses. In general the cost groupings established within a category should constitute a pool of items of expense that are considered to be of like nature in terms of their relative contribution to the particular cost objectives to which distribution is appropriate (A-21, section E). Cost categories should be established considering the general guidelines in A-21, section E.2.c.

e. Indirect costs are defined into two broad categories in A-21, section F.

(1) “Facilities” is defined as depreciation and use allowance, interest in debt associated with certain buildings, equipment, and capital improvements, operation and maintenance expenses, and library expenses.

(2) “Administration” is defined as general administration and general expenses, departmental administration, sponsored project administration, student administration and services, and all other types of expenditures not listed specifically under one of the facility categories.

f. Each educational institution’s indirect cost rate process must be appropriately designed to determine that Federal sponsors do not in any way subsidize the indirect costs of other sponsors, specifically activities sponsored by industry and foreign governments (A-21, section G.).

g. Administrative costs charged to sponsored agreements awarded or amended with effective dates beginning on or after the start of the educational institution’s first fiscal year which begins on or after October 1, 1991, shall be limited to 26 percent of modified total direct costs, as defined in A-21, section G.2. Educational institutions should not change their accounting or cost allocation methods which were in effect on May 1, 1991, if the effect is to (1) change the charging of a particular type of cost from indirect to direct, or (2) reclassify or increase allocations from the administrative pools to the facilities pools or fringe benefits cost pools (but also see A-21, section G.8).

h. Submission Requirement for Standard Format for Long-Form ProposalsEducational institutions shall use the standard format shown in A-21, Appendix C to submit ICRP to the cognizant agency for indirect costs. The cognizant agency for indirect costs may, on an institution-by-institution basis, grant exceptions from all or portions of Part II of the standard format. This requirement does not apply to educational institutions that use the simplified method for calculating indirect cost rates, as described in A-21, section H.

2. Audit Objectives – Indirect Costs

a. For educational institutions that charge indirect costs to Federal awards based on federally approved rate(s):

(1) Obtain an understanding of internal control, assess risk, and test internal control as required by OMB Circular A-133 §___.500(c).

(2) Determine that the rate(s) used to charge indirect costs is consistent with the appropriate cognizant Federal agency rate agreement (A-21, section G.11).

(3) Determine that the federally approved rate in effect at the time of the initial award is applied throughout the life of the sponsored agreement. “Life” means each competitive segment of a project. A competitive segment is a period of years approved by the Federal-funding agency at the time of the award (A-21, section G.7).

(4) Determine that the federally approved rate(s) were applied to the appropriate distribution base (A-21, section G.2).

(5) Determine that indirect costs billed to sponsored agreements are the result of applying the approved rate(s) to the appropriate base amount(s).

b. For educational institutions that charge indirect costs to Federal awards based on rate(s) which are not approved by the cognizant Federal agency:

(1) Obtain an understanding of internal control, assess risk, and test internal control as required by OMB Circular A-133 §___.500(c).

(2) Determine the educational institution’s cognizant Federal agency for approving indirect cost rates in accordance with A-21, section G.11.

(3) Determine whether an ICRP was prepared, certified, and submitted by the educational institution to their cognizant Federal agency. (The Federal agency is responsible for negotiating and approving indirect cost rates). Verify that billings are based on the ICRP.

(4) Determine that the submitted rate(s) were applied to the appropriate distribution base (a-21, section G.2).

(5) Determine that indirect costs billed to sponsored agreements are the result of applying the submitted rate(s) to the appropriate base amount(s).

c. For educational institutions that charge indirect costs to Federal awards based on award-specific rate(s) approved by an awarding agency:

(1) Obtain an understanding of internal control, assess risk, and test internal control as required by OMB Circular A-133 §___.500(c).

(2) Determine that the award-specific rate(s) are the result of special circumstances such as required by law or regulation, in accordance with


A-21, section G.11.

(3) Determine whether indirect cost rates were applied in accordance with the approved special award provisions or limitations. Associated billings were the result of applying the approved rate to the proper base amount.

(4) When the maximum amount of allowable indirect costs under a limitation (i.e. an award-specific rate) is less than the total amount determined in accordance with the principles in A-21, the amount not recoverable under a sponsored agreement may not be charged to other sponsored agreements (A-21, section C.7).

3. Suggested Internal Control Audit Procedures – Indirect Costs

a. Using the guidance provided in Part 6 – Internal Control, perform procedures to obtain an understanding of internal control sufficient to plan the audit to support a low assessed level of control risk for the program.

b. Plan the testing of internal control to support a low assessed level of control risk for allowable costs/cost principles and perform the testing of internal control as planned. If internal control over some or all of the compliance requirements is likely to be ineffective, see the alternative procedures in §___.500(c)(3) of OMB Circular A-133, including assessing the control risk at the maximum and considering whether additional compliance tests and reporting are required because of ineffective internal control.

c. Consider the results of the testing of internal control in assessing the risk of noncompliance. Use this as the basis for determining the nature, timing, and extent (e.g., number of transactions to be selected) of substantive tests of compliance.



4. Suggested Compliance Audit Procedures – Indirect Costs

a. Test a sample of transactions for conformance with the following criteria contained in A-21 and CAS, as applicable.

b. For educational institutions that charge indirect cost to Federal awards based on federally approved rate(s):


  1. Ascertain if indirect costs or centralized or administrative services costs were allocated or charged to a major program. If not, the following suggested audit procedures do not apply.

  2. Obtain and read the current indirect cost rate agreement and determine the terms in effect.

  3. Select a sample of claims for reimbursement and verify that the rates used are in accordance with the rate agreement, that rates were applied to the appropriate bases, and that the amounts claimed were the product of applying the rate to the applicable base. Verify that the costs included in the base(s) are consistent with the costs that were included in the base year (e.g., if the allocation base is total direct costs, verify that current year direct costs do not include costs items that were treated as indirect costs in the base year).

  4. Ascertain if the educational institution’s accounting practices for determining direct and indirect costs for the fiscal year being audited are consistent with the accounting practices used to establish the federally approved rate and its DS-2. If there accounting changes have occurred, determine if they were approved by the cognizant Federal agency. If accounting changes have not been approved and the accounting changes impact costs charged to federally funded awards, this should be considered a reportable finding. (A-21, section C.14 and CAS, as applicable).

c. For educational institutions that charge indirect cost to Federal awards based on rate(s) which are not approved by the cognizant Federal agency:

(1) If the ICRP has been certified and submitted to the cognizant Federal agency and is based on costs incurred in the year being audited, then the ICRP should be audited for compliance with the provisions of A-21 and CAS, as applicable.

(2) If the educational institution has a certified ICRP, which is based on costs incurred in the year being audited, but has not submitted it to their Federal cognizant agency. The ICRP should be audited using the procedures listed below.

(a) Test the indirect cost pool groupings for compliance with A-21, section F.

(b) Test the indirect cost pools to determine if costs are allowable.

(c) Test that indirect costs have been treated consistently when incurred for the same purpose, in like circumstances, as indirect costs only with respect to final cost objectives. No final cost objective shall have allocated to it as a cost any cost, if another cost incurred for the same purpose, in like circumstances, has been included as a direct cost of that or any other final cost objective (A-21, section C.11).

(d) Test that the indirect cost pools in the rate proposal were developed consistent with the educational institution’s disclosed practices as described in its DS-2, if applicable (A-21, section C.14).

(e) Test the depreciation and use allowance cost pool to determine if:

(i) Computations of depreciation or use allowance are based on the acquisition cost of the assets. Acquisition costs exclude (A) the cost of land; (B) any portion of the cost of buildings and equipment borne by the Federal Government, irrespective of where title was originally vested or where it is presently located; and (C) any portion of the cost of buildings and equipment contributed by or for the educational institution where law or agreement prohibit recovery (A-21, section J.14).

(ii) The depreciation method used to charge the cost of an asset (or group of assets) to accounting periods reflects the pattern of consumption of the asset during its useful life


(A-21, section J.14).

(iii) Charges for use allowances or depreciation are supported by adequate property records and physical inventories, which must be taken at least once every 2 years (A-21, section J.14).

(iv) The depreciation methods used to calculate the depreciation amounts for the ICRP are the same methods used by the educational institution for its financial statements (A-21, section J.12).

(v) The allocation method for the depreciation and use allowance cost pool complies with A-21, section F.2.

(vi) Gains and losses on the sale, retirement, or other disposition of depreciable property have been appropriately accounted for and complies with A-21, section J.21.

(vii) Large research facilities – Determine that large research facilities that are included in ICRPs negotiated after January 1, 2000, and on which the design and construction began after July 1, 1998, are compliant with the provisions for determining allowable costs in A-21, section F.2.c.

(f) Test the interest cost pool to determine if:

(i) Computations for interest comply with the provisions of


A-21, section J.26.

(ii) The allocation method for the interest cost pool complies with A-21, section F.3.

(g) Test the operations and maintenance cost pool to determine if:

(i) Costs are appropriately classified in this cost pool


(A-21, section F.4).

(ii) Rental costs comply with the provision of A-21, section J.43.

(iii) The educational institution’s accounting practices for classifying (A) rearrangement and alteration costs and
(B) reconversion costs, either as direct or indirect, result in consistent treatment in like circumstances.

(iv) The allocation method for the operations and maintenance cost pool complies with A-21, section F.4.

(h) Tests the library cost pool to determine if:

(i) Costs are appropriately classified in this cost pool (A-21, section F.8).

(ii) The allocation method for the library cost pool complies with A-21, section F.8.

(iii) If the allocation method is based on a cost analysis study in accordance with A-21, section E.2.d, determine that the study:

(A) Results in an equitable distribution of costs and represents the relative benefits derived,

(B) Is appropriately documented in sufficient detail for review by the cognizant Federal agency,

(C) Is statistically sound,

(D) Is performed specifically at the educational institution,

(E) Is reviewed every 2 years, and, if necessary, updated, and

(F) Assumptions are clearly stated and adequately explained.

(i) Test the administrative cost pools to determine if:

(i) Costs are appropriately classified in these cost pools and the distribution bases are compliant with A-21, sections F.5, F.6, and F.7.

(ii) The administrative cost components comply with the limitation on reimbursement of administrative cost in A-21, section G.8. If the proposal is based on the alternative method for administrative cost in A-21, section G.9, then the limitation does not apply. If the proposal is based on the alternative method for administrative cost, determine that the educational institution meets the criteria of section G.9 and that this is adequately documented in the proposal.

(iii) Departmental administration expense pool – test to determine that this cost pool complies with A-21, section F.6.

(iv) Academic Deans’ Offices – test that salaries and operating expenses are limited to those attributable to administrative functions.

(v) Academic Departments – Salaries and fringes attributable to the administrative work (including bid and proposal preparation) of faculty (including department heads), and other professional personnel conducting research and/or instruction, is allowed at a rate of 3.6 percent of modified total direct costs. This category should not include professional business or administrative officers. Determine that this allowance is added to the computation of the indirect cost rate for major functions. Test to determine that the expense covered by this allowance are excluded from the departmental cost pool (A-21, section F.6).

Test for consistent treatment, in like circumstances, of other administrative and supporting expenses incurred within academic departments. For example, items such as office supplies, postage, local telephone, and memberships shall normally be treated as indirect costs.

(3) If the ICRP has been certified and submitted to the cognizant Federal agency, but is based on costs incurred in a fiscal year prior to the fiscal year being audited, a review of the ICRP is not required.

(4) If an ICRP has not been prepared and, therefore, the indirect costs charged to Federal awards are not based on a certified ICRP, this may be required to be reported as an audit finding, in accordance with OMB Circular A-133, §__.510(a)(5).

(5) Application of an indirect cost rate(s) not approved by the cognizant agency – Even though the rate(s) has not been approved by the cognizant agency, an unapproved indirect cost rate(s) should be reviewed for consistent application of the submitted rates to direct cost bases to ensure that the indirect cost rate(s) is applied consistent with the educational institution’s policies and procedures that apply uniformly to both federally funded and other activities of the institutions.

d. For educational institutions that also have awards containing award-specific rates (approved by the Federal awarding agency) that take precedence over the negotiated rate for purposes of indirect cost recovery:

(1) Ascertain that the award-specific rate is in accordance with special circumstances required by law or regulation.

(2) Obtain and review the award terms used to establish an award-specific indirect cost rate(s).

(3) Select a sample of claims for reimbursement and verify that the award-specific rate(s) used are in accordance with the terms of the award, that rate(s) were applied to the appropriate bases, and that the amounts claimed were the product of applying the rate to the applicable base. Verify that the costs included in the base(s) are consistent with the terms of the agreement.